We take technical projects from inventory and assessment through to execution — managing cost, quality, and delivery for renovation, new construction, and infrastructure installation.
Design and deployment of integrated energy systems — BESS, vertical wind turbines, and DC-DC EV charging — structured for maximum revenue generation and minimum operational burden on the property owner.
Detailed technical investigation before replacing or installing equipment — with clear proposals, cost estimates, and a view on what will increase property value over 5 and 10 years.
Support for procurement processes under the Swedish Public Procurement Act and the Act on Procurement in the Utility Sector.
Reference cases
Design a self-sufficient parking garage with current charging options and future expansion. 4 vertical wind turbines, 860 kWh battery storage, 20 × 22 kW and 2 × 240 kW DC-to-DC EV chargers — eliminating approximately 30% conversion losses. Result: future-proof, energy-efficient parking garage with fast, stable, sustainable vehicle charging and increased revenue.
Increase revenue and reduce power tariffs for an existing wind turbine installation. 500 kW / 1,000 kWh battery storage system integrated with the existing turbine. Result: future-proofed against high power tariffs, with increased arbitrage opportunity and frequency support service revenue.
Redesign a stopped three-blade wind project in Europe. 160 vertical wind turbines of 100 kW each, paired with a 74 MWh battery storage system. Result: wind power with battery storage for production, electricity trading, curtailment management, balancing, and frequency regulation.
Design and implementation of a locally produced energy solution using vertical wind power for direct electricity use within the apartments. Result: future-proof, energy-efficient local production with a stable and sustainable supply for residents.
Further reference work
Investigation, proposed measures, and implementation management for heating and electricity errors in industrial buildings. Over $10,000 annual savings.
Replacement of older ventilation systems, optimisation across tenant premises, and replacement of heat exchangers for improved facility-wide economy.
Fault in ramp construction at a port facility. Action plan and project leadership through remediation.
Three-person project management team for the new construction of two state-of-the-art Platform Supply Vessels.
Project manager on the municipality client side for an 11,000 m² logistics facility with approximately 90,000 m² land area.
Client technical and documentation support during due diligence for the sale of 5 properties totalling $12.8 million.
Rainwater management plan and implementation to minimise load on surrounding areas and the city pipe system.
Project manager for the reinforcement of 193 concrete piles during quay construction for an industrial port.
Prepared documentation and data for green building and environmental certification of 1982-era buildings.